VW Touareg repair+ 1. Operation and car maintenance + 2. Engine - 3. Transmission + 6-step automatic transmission 09D - Hydrotransformer check Liquid pumping from the hydrotransformer Hydrotransformer installation Repair of a drive of gear shifting Removal and installation of the handle of the selector Check and adjustment of draft of the selector Removal and installation of draft of the selector Removal and slip installation Removal and frame installation Removal and installation of an electromagnet of blocking of the N110 selector Removal and installation of the switch of the selector (the lever is blocked in the situation "P") F319 Removal and installation of a drive of gear shifting Removal and transmission installation, cars with the diesel R5 engine Removal and transmission installation, cars with petrol V6 and V8 engines, turbodiesel engines V6 TDI, V10 TDI and the petrol W12 engine Inhaling moments Removal and installation of highways and ATF radiator Removal and installation of the control unit of an automatic transmission of J217 Replacement of a sealing ring of a secondary shaft Removal and installation of the oil pallet Removal and installation of the mesh oil filter Removal and installation of the sensor of pressure for hydrosystem 1 in AKP G193 and the pressure sensor for hydrosystem 2 in AKP G194 Removal and installation of a zolotnikovy box Removal, installation and adjustment of the multipurpose F125 switch + Mechanical transmission 08D and transfer case Е473 + Driveshaft + Driving mechanism + Tables + 4. Running gear + 5. Steering mechanism + 6. Brake system + 7. Onboard electric equipment + 8. Body + electric equipment Schemes |
Volkswagen Touareg / Touareg repair>> Transmission>> Hydrotransformer check>> Removal and installation of a drive of gear shifting
Removal
Remove the selector handle.
Pull draft up and switch the selector in the situation "S".
It is necessary to observe sequence of shutdown of joint stock bank surely.
Disconnect the mass plug from joint stock bank at the switched-off ignition.
Remove the central console.
Take a noise isolation from the central console.
Unblock and disconnect the tip 1.
Unscrew a bolt 2 and remove the holder.
Take shtekerny connection 3 of the holder
(fig. 3.23)
.
Disconnect the tip 1.
Carefully disconnect clamps 2 at the left and to the right of a frame
(fig. 3.15)
.
Pull clamps at the left and on the right outside and pull a frame up
(fig. 3.16)
.
Unscrew tightening a bolt on draft of the selector by means of T40031 nozzle
(fig. 3.12)
.
Unscrew bolts 1 and remove the forward holder 2 drives of switching
(fig. 3.26)
.
Remove the back holder of a drive of gear shifting.
Pull a gear shifting drive together with draft of the selector a little back.
Remove a lock washer 2 from draft of the selector 1 and disconnect a gear shifting drive from draft of the selector
(fig. 3.27)
.
Installation
Installation is carried out in return sequence. Thus it is necessary to consider the following.
Establish draft of the selector 1 and fix by means of a new lock washer 2.
Fasten forward and back holders of a drive of gear shifting
(fig. 3.27)
.
To lay cables 1–3 how it is shown in drawing
(fig. 3.25)
.
Establish shtekerny connection 3 in the holder.
Tighten a bolt 2.
Connect the tip 1
(fig. 3.23)
.
Adjust draft of the selector
Establish the central console.
Connect joint stock bank.
Establish the selector handle
|
< |